ALLENTOWN, Pa. — State environmental regulators will hold a public meeting and hearing Monday, Nov. 23, at Cedar Crest College on permits for Project Atlas, a proposed large-scale data center campus in South Whitehall Township.
The Pennsylvania Department of Environmental Protection session is set for Alumnae Hall Auditorium, Building 2, at 100 College Drive in Allentown, according to South Whitehall Township and state public notices.
The evening is split into two parts. From 5:30 p.m. to 7:30 p.m., department staff will host an informational meeting and take general questions about the project and permitting process. A formal public hearing follows from 7:45 p.m. to 9:30 p.m. for residents who want to enter official spoken testimony into the state permit record.
Monday’s review is a key state checkpoint for the proposed 1.5 million-square-foot campus, which developer CDE Acquisitions LLC, an affiliate of Edged, plans to build on roughly 410 acres across from Parkland High School. The project has sparked sustained local pushback over its scale and potential effects on nearby neighborhoods and schools.
At stake are two state environmental permits covering construction stormwater runoff and work near wetlands and local waterways, including tributaries of Coplay Creek and Jordan Creek. Regulators are reviewing a Chapter 105 water obstruction and encroachment permit, Application No. E3902226-002, and an individual National Pollutant Discharge Elimination System stormwater permit, Application No. PAD390390, according to state filings.
The property sits near North Cedar Crest Boulevard, Mauch Chunk Road and Orefield Road. Under the revised proposal, Project Atlas calls for three primary data center buildings, an administration building, a warehouse, an electrical substation and backup emergency generators. Earlier concepts for the site envisioned a much larger footprint before the developer scaled back its plans.

Opposition has come from the Parkland School District alongside local and national advocacy groups, including the South Whitehall Civic Alliance, Food & Water Watch and Lehigh Valley Stands Up. Critics point to the site’s proximity to Parkland High School, as well as concerns over heavy electricity demand, backup generators, noise and potential impacts on local water resources.
The state permit review is moving forward alongside local township proceedings. Following an earlier township review, the South Whitehall Township Planning Commission placed the land development plan under advisement, holding off on a decision after a crowded special meeting at Parkland High School over unresolved engineering and safety review comments.
Monday’s hearing also lands amid a wider debate over artificial intelligence infrastructure across the Lehigh Valley. Earlier this month, the Bethlehem Planning Commission voted 5-0 to approve land development plans for a separate data center on Industrial Drive after hours of public opposition, while Upper Mount Bethel Township officials continue reviewing large-scale data center proposals for the former River Pointe site.